Work on the 2nd phase of Fábrica 1921 continues, with the installation of the frames and application of glass in the opening. Exterior plastering and the application of thermal insulation

Fábrica 1921 has been recognized with the National Urban Rehabilitation Award 2023. This achievement is proof of the commitment, ingenuity, experience, and excellent work carried out by Teixeira Duarte Real

The construction is progressing according to plan. So far, the building structure has been completed, ensuring a solid foundation, and the masonry works have been finished, contributing to the structural

With the progress in the development of the building structure completed, the construction continues with the finalization of the technical coverings and the pool. Additionally, with the masonry works already

MAY 2022: FIRST BUILDING’S SLAB

The reinforced concrete structure's works continues. The slab of -2 floor is concluded and the preparation of -1 floor slab is taking place.

FEBRUARY 2022: COMPLETION OF EXCAVATION

In February, excavation work was completed on the second phase of FÁBRICA 1921.

DECEMBER 2021: COMPLETION OF THE PERIPHERAL CONTAINMENT WALL

This month, the peripheral containment wall was completed and the excavation process and respective anchorages started.

NOVEMBER 2021: START OF EXCAVATION AND CONTAINMENT WORKS

A new chapter of FÁBRICA 1921 began, with the beginning of excavation and containment work in the new condominium.