MAY 2022: FIRST BUILDING’S SLAB

The reinforced concrete structure's works continues. The slab of -2 floor is concluded and the preparation of -1 floor slab is taking place.

APRIL 2022: FACADE AND INFRASTRUCTURES

In April the work on the facade and the infrastructures is getting noticed.

FEBRUARY 2022: COMPLETION OF EXCAVATION

In February, excavation work was completed on the second phase of FÁBRICA 1921.

FEBRUARY 2022: CARPENTRY BEGINNING

In February, work began on the interior carpentry of the apartments, namely kitchen cabinets, wardrobes and doors.

JANUARY 2022: REHABILITATION OF THE OLD FAÇADE

In January, a very important milestone was reached in FÁBRICA 1921, with the completion of the first phase of rehabilitation of the old façade. This façade preserves the memory of Fábrica Simões and, with its renovation, begins a new chapter.

DECEMBER 2021: START OF WOODEN FLOORING

The placement of wooden floors inside the apartments began, as well as the installation of wardrobes.

DECEMBER 2021: COMPLETION OF THE PERIPHERAL CONTAINMENT WALL

This month, the peripheral containment wall was completed and the excavation process and respective anchorages started.