SPACES FOR RELAXING WITH A GOOD BOOK

  • ALL NEWS
  • FASES DA OBRA: 1ª fase
  • FASES DA OBRA: 2ª fase
  • NEWS
MAY 2023: NATIONAL URBAN REHABILITATION AWARD 2023

Fábrica 1921 has been recognized with the National Urban Rehabilitation Award 2023. This achievement is proof of the commitment, ingenuity, experience, and excellent work carried out by Teixeira Duarte Real …

APRIL 2022: FACADE AND INFRASTRUCTURES
APRIL 2022: FACADE AND INFRASTRUCTURES

In April the work on the facade and the infrastructures is getting noticed. …

FEBRUARY 2022: CARPENTRY BEGINNING
FEBRUARY 2022: CARPENTRY BEGINNING

In February, work began on the interior carpentry of the apartments, namely kitchen cabinets, wardrobes and doors. …

JANUARY 2022: REHABILITATION OF THE OLD FAÇADE
JANUARY 2022: REHABILITATION OF THE OLD FAÇADE

In January, a very important milestone was reached in FÁBRICA 1921, with the completion of the first phase of rehabilitation of the old façade. This façade preserves the memory of …

DECEMBER 2021: START OF WOODEN FLOORING
DECEMBER 2021: START OF WOODEN FLOORING

The placement of wooden floors inside the apartments began, as well as the installation of wardrobes. …

AUGUST 2021: FINISHES AND STUCCO’S DEVELOPMENT
AUGUST 2021: FINISHES AND STUCCO’S DEVELOPMENT

In August, the finishing and stucco works continue at a good pace in the construction work of FÁBRICA 1921. …

JULY 2021: FINISHES AND STUCCO
JULY 2021: FINISHES AND STUCCO

The construction work of FÁBRICA 1921 is proceeding at a good pace with the stucco work. …

MAY 2021: WORK’S DEVELOPMENT
MAY 2021: WORK’S DEVELOPMENT

In May, work began on the preparation of the renovation of the old façade. …

FEBRUARY 2021: WORK’S DEVELOPMENT ON BUILDING STRUCTURE
FEBRUARY 2021: WORK’S DEVELOPMENT ON BUILDING STRUCTURE

With the recent completion of the F core structure, the work on the structure's execution for the entire project is almost completed. …

JANUARY 2021: WORK’S DEVELOPMENT ON BUILDING STRUCTURE
JANUARY 2021: WORK’S DEVELOPMENT ON BUILDING STRUCTURE

In FÁBRICA 1921, the construction works continue at a good pace, with the F core practically completed at the structure level. …

September 2023: Completion of the Water Supply Network

Work on the 2nd phase of Fábrica 1921 continues, with the installation of the frames and application of glass in the opening. Exterior plastering and the application of thermal insulation …

MAY 2023: NATIONAL URBAN REHABILITATION AWARD 2023

Fábrica 1921 has been recognized with the National Urban Rehabilitation Award 2023. This achievement is proof of the commitment, ingenuity, experience, and excellent work carried out by Teixeira Duarte Real …

April 2023: Completion of the masonry works

The construction is progressing according to plan. So far, the building structure has been completed, ensuring a solid foundation, and the masonry works have been finished, contributing to the structural …

February 2023: Completion of the building structure

With the progress in the development of the building structure completed, the construction continues with the finalization of the technical coverings and the pool. Additionally, with the masonry works already …

MAY 2022: FIRST BUILDING’S SLAB
MAY 2022: FIRST BUILDING’S SLAB

The reinforced concrete structure's works continues. The slab of -2 floor is concluded and the preparation of -1 floor slab is taking place. …

APRIL 2022: CONCRETE WORKS DEVELOPMENT
APRIL 2022: CONCRETE WORKS DEVELOPMENT

FEBRUARY 2022: COMPLETION OF EXCAVATION
FEBRUARY 2022: COMPLETION OF EXCAVATION

In February, excavation work was completed on the second phase of FÁBRICA 1921. …

JANUARY 2022: WORK’S DEVELOPMENT
JANUARY 2022: WORK’S DEVELOPMENT

DECEMBER 2021: COMPLETION OF THE PERIPHERAL CONTAINMENT WALL
DECEMBER 2021: COMPLETION OF THE PERIPHERAL CONTAINMENT WALL

This month, the peripheral containment wall was completed and the excavation process and respective anchorages started. …

NOVEMBER 2021: START OF EXCAVATION AND CONTAINMENT WORKS
NOVEMBER 2021: START OF EXCAVATION AND CONTAINMENT WORKS

A new chapter of FÁBRICA 1921 began, with the beginning of excavation and containment work in the new condominium. …

10 shops that make Benfica a typical Lisbon neighbourhood
10 shops that make Benfica a typical Lisbon neighbourhood

Freshly ground coffee, sweet pastries coveted even by the competition, award-winning Portuguese custard pies, ice cream with insect topping and a fresh produce market where they call you by your …

Memories of those who worked at the Simões Factory
Memories of those who worked at the Simões Factory

Lurdes is 72 years old and Celeste, 73, friends for 60 years, remember what it was like to work in one of the biggest factories on the Iberian peninsula. …

Is Benfica one of Lisbon’s last traditional neighbourhoods?
Is Benfica one of Lisbon’s last traditional neighbourhoods?

There are 4 km of road between the Portas de Benfica and the Zoological Gardens and we decided to walk the whole distance. Here are the must-visit places on Estrada …

From nursery school to higher education without leaving the neighbourhood
From nursery school to higher education without leaving the neighbourhood

"Benfica is a unique parish", says Ricardo Marques, parish council member for Education and Training. “All levels of education can be found here”, with a total of 32 schools, if …

  • ALL NEWS
  • FASE: DA OBRA: 1ª fase
  • FASE: DA OBRA: 2ª fase
  • NEWS
MASONRY – VIDEO
MASONRY – VIDEO

With the beginning of the masonry, we were able to see the shape of the future FÁBRICA 1921 apartments. An important milestone that demonstrates the pace and our commitment in …